Recurring Goals

Our schedule is beginning to fill out. We would like to allot one hour every day to administrative time, which includes breaks and checking email. We will need to add this in for every day. Microsoft Project 98 allows us to add recurring goals.

Click on the next empty row (number 9) and go to Insert in the menu. Select Recurring Task:

Enter the following information in the Recurring Goal Information form:

Goal Name

Duration

From

To

This occurs

Daily

Administrative

1h

01/15/02

Wed 01/15/03

Daily

Every Workday

Press OK. Select goal 9 and click on the left arrow to move Administrative up one level. Your schedule should now look as follows:

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment