Project network of activities

The (condensed) network planning consists of about 190 activities. Most of the activities have a Finish to Start relation. Some have a Finish to Finish relation. Some activities are partly completed as the project is assumed to be still in progress.

The deterministic approach is used to identify the critical path which has no slack. Then the other paths are ranked based on the total slack each has.

The probabilistic approach is used to rank paths on risk. This approach uses not only estimates on the expected duration of each activity, but also pessimistic and optimistic estimates. A Monte Carlo simulation can then be carried out using these estimates to rank paths on risk.

Real Estate Essentials

Real Estate Essentials

Tap into the secrets of the top investors… Discover The Untold Real Estate Investing Secrets Used By The World’s Top Millionaires To Generate Massive Amounts Of Passive Incomes To Feed Their Families For Decades! Finally You Can Fully Equip Yourself With These “Must Have” Investing Tools For Creating Financial Freedom And Living A Life Of Luxury!

Get My Free Ebook


Post a comment