Long Lead Items

Long lead items are those materials, products, or equipment that when initially ordered may fall outside a designated milestone date for when they should be at the job site. See Exhibit 15-13 for the long lead items flow chart.

During the design phase, the design team should indicate those materials, products, or equipment where potential scheduling problems could exist. The PM and the purchasing department should review the design documents and prepare a list of the potential long lead items. All critical items should be reviewed with the owner with the recommendation that these items are purchased immediately. These items, once purchased, would then be assigned to the approved subcontractor responsible for the installation. Once the subcontractors are selected, confirmation should be obtained from them as to the availability of additional potential critical items not purchased initially. The subcontractors should also give notice of any other items that either are no longer fabricated or will create a potential scheduling problem. To track the process of the long lead item from shop log submittal to design team approval the long lead item tracking log depicted in Exhibit 15-14 should be utilized. After the long lead items have been ordered, they

Long lead item

Review design documents

Prepare list of long lead items

Review design documents

Prepare list of long lead items

Long Lead Items

Exhibit 15-13

Long lead item flow diagram.

Long Lead Item

Date Required At Job Site

Shop Drawing Submittal Date

Shop Drawing Approval Date

Shop Drawing Returned to Sub

Start Fabrication

Complete Fabrication

Ship Date

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

Long lead items tracking schedule.

03 O

Material

Job Required Date

Confirmation By Name

Date

Confirmation By Name

Date

Confirmation By Name

Date

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

Tracking long lead items log.

1. Steel for a structure

2. Concrete

Exhibit 15-16

Potential long lead items.

3. Pre-cast components

4. Reinforcing steel

5. Copper piping and wire

6. Curtain walls

7. Elevators

8. Escalators

9. Some landscaping material

10. Paving (plants close down for the winter)

11. Hardware

12. Special light fixtures

13. Millwork

14. Wood doors

15. Special ceilings (i.e., metal)

16. Vinyl wall coverings

17. Carpet

18. Mechanical units (especially chillers and cooling towers)

19. Transformers and switchgear

20. Glass doors

21. Stone for walls, floors, and paving

22. Special fabrications (railings, architectural finishes, etc.)

23. Roofing material

24. Products coming from a foreign country

25. Materials that are going to foreign countries should be tracked on a continuous basis. A follow-up log is indicated in Exhibit 15-15. The list of potential long lead items is noted in Exhibit 15-16.

In order for the CM/GC and the subcontractors to keep track of the schedule on a continuous basis, it is a good idea to break down the schedule into two-week increments. In this way, all the participants can focus on the activities that have to be accomplished within the next two weeks. In addition, any milestone dates would be noted on the two-week look ahead schedule. The milestone dates would be those activities that must be accomplished in order to meet the schedule end date. This is not to say that you forget about the main schedule because you never want to lose sight of the big picture—the completion of the project and the related milestone dates. Exhibit 15-17 shows the elements for preparing a two-week look ahead schedule.

Was this article helpful?

0 0
Homeowners Guide To Landscaping

Homeowners Guide To Landscaping

How would you like to save a ton of money and increase the value of your home by as much as thirty percent! If your homes landscape is designed properly it will be a source of enjoyment for your entire family, it will enhance your community and add to the resale value of your property. Landscape design involves much more than placing trees, shrubs and other plants on the property. It is an art which deals with conscious arrangement or organization of outdoor space for human satisfaction and enjoyment.

Get My Free Ebook


Responses

  • gundahar goodbody
    What is a long lead item?
    11 months ago
  • Alanna
    What are the process in long lead items?
    6 months ago
  • martino
    What is considered a long lead item?
    6 months ago
  • ANTONIA
    What is considered long lead items?
    5 months ago
  • fortinbras
    Are shop drawings part of long lead items?
    3 months ago
  • lewis
    What are my normal long lead items in construction?
    2 months ago

Post a comment