Multiproject PRT Additions

The multiproject PRT therefore requires adding the following intermediate objectives:

1. The drum resource is selected.

2. The drum manager is identified.

3. Initial project priorities are assigned.

Figure 11.9 CRT additions for multiproject.

4. Management commits to new project-completion dates only after deciding the new project priority (relative to ongoing projects), developing the new project plan, and scheduling through the drum resource (pipelining).

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.