figure 3: Schedule for Project 13 without resource leveling.

Timeline's placement of Tasks 17 and 18, which are milestone activities of negligible duration. On the fourth day, there is a shortage of the second resource, calling for a decision. Tasks 3 and 5, which started on Days 1 and 3, respectively, use six of the ten available units of this resource on Day 4. Task 6 requires three units and Task 11 requires four units of the second resource. Table 3 reveals that some packages schedule Task 6 here, while others schedule Task 11.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.