Note that three activities can start immediately. Find:

(a) The critical path.

(b) The earliest time to complete the project,

(d) Draw the network on a Gantt chart.

14. The events of the project below are designated as 1, 2, and so on.

(a) Draw the PERT network and the Gantt chart.

(b) Find the critical path.

(c) Find the slacks on all the events and activities.

Find:

(a) The probability of completing this project in 12 weeks (or less).

(b) The probability of completing this project in 13 weeks (or less).

(c) The probability of completing this project in 16 weeks (or less).

(d) The number of weeks required to assure a 92.5 percent chance of completion.

13. Given a PERT network:

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.