Now as it might happen, and often does, as the work package manager is working on a pair of tasks such as we just analyzed, along comes Task C. Task C is unplanned for the current period; Task C is planned for Period 2. Nonetheless, the decision is made to work on Task A and C and let Task B go to the next period. This situation is illustrated in Figure 6-3. Only Task A is completed in Period 1. Work is started in Period 1 on Task C, but not completed; Task C will be completed in Period 2. Task B is deferred to Period 2.

Figure 6-3: Three-Task Two-Period Example.
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.