Cocomo A Regression Model

The Constructive COst MOdei (COCOMO) is arguably the most widely used estimating technique. It is a regression-based model developed by Dr. Barry W. Boehm when he was at TRW in the early 1970s. He began by analyzing 63 software projects of various types. The projects were observed for actual size (LOC), actual effort expended, and actual schedule duration. Regression analysis was then used to develop exponential equations that best describe the relationship between the scattered data points.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.