Relying on network templates

Creating a PND sounds like a bunch of work because it is a bunch of work. Planning the sequence of activities takes time and effort. In addition, heated debates, conflicts, and open issues can hinder how the work progresses.

Now for some good news: If you do the same type of work over and over, you don't have to start from scratch every time. Instead, you can create a project network diagram template. A template, as you know, is a standardized document that has basic information and common activities already filled in. A good template just requires you to fill in the correct dates for the major activities your team performs.

You can easily create a template by using a past project of similar work. The catch, however, is that you'll also want to review the lessons learned from the past project to ensure that the work on your next project goes as expected. Great templates are made, not born. The network template should be accurate, yet fluid, so that you can adapt it to each future project.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment