Typical Cocomo Project Profile

The following discussion focuses on a specific example project in order to illuminate some of the project planning implications. Assume a large, 100,000 source-line (100-KDSI) mission-critical system (for example, control of a power plant) built under contract for a government agency. Figure B-l illustrates the COCOMO-estimated profile for this project. COCOMO would estimate 900 staff-months for development plus 72 staff-months for requirements specification for this project. The schedule required would be 22 months from initiation of design through test, plus 8 months for requirements.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.