Construction began without a signed agreement from Continental and United. Early Risk Analysis

By March of 1991, the bidding process was in full swing for the main terminal, concourses, and tunnel. Preliminary risk analysis involved three areas: cost, human resources, and weather.

• Cost: The grading of the terminal area was completed at about $5 million under budget and the grading of the first runway was completed at about $1.8 million under budget. This led management to believe that the original construction cost estimates were accurate. Also, many of the construction bids being received were below the city's own estimates.

• Human Resources: The economic recession hit Denver a lot harder than the rest of the nation. DIA was at that time employing about 500 construction workers. By late 1992, it was anticipated that 6000 construction workers would be needed. Although more than 3000 applications were on file, there remained the question of available, qualified labor. If the recession were to be prolonged, then the lack of qualified suppliers could be an issue as well.

• Bad Weather: Bad weather, particularly in the winter, was considered as the greatest risk to the schedule. Fortunately, the winters of 1989-1990 and 1990-1991 were relatively mild, which gave promise to future mild winters. Actually, more time was lost due to bad weather in the summer of 1990, than in either of the two previous winters.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment