Estimating Total Program Time

In order to calculate the probability of completing the project on time, the standard deviations of each activity must be known. This can be found from the expression:

where is the standard deviation of the expected time, te. Another useful expression is the variance, v, which is the square of the standard deviation. The vari-

7 It is assumed that the functional manager performs all of the estimating. The reader should be aware that there are exceptions where the program or project office would do their own estimating.

8 See F. S. Hillier and G. J. Lieberman, Introduction to Operations Research (San Francisco: Holden-Day, 1967), p. 229.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment