The Cumulative Average Curve

It is common practice to plot the learning curve on log-log paper but to calculate the cumulative average from the following formula:

where

Tx = the direct labor hours for unit n T1 = the direct labor hours for the first unit (unit one) X = the cumulative unit produced —K = a factor derived from the slope of the experience curve

Typical values for the exponent K are:

Learning curve % 100 95 90 85 80 75 70

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.