FIGURE 12-10. Slack time.

sured from the customer's completion date, thus creating negative slack. This is most likely to result when:

• The original plan was highly optimistic, but unrealistic

• The customer's end date was unrealistic

• One or more activities slipped during project execution

• The assigned resources did not possess the correct skill levels

• The required resources would not be available until a later date

In any event, negative slack is an early warning indicator that corrective action is needed to maintain the customer's end date.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.