c. What is the total slack time in the network?

d. What is the expected time for 68, 95, and 99 percent completion limits?

e. If activity G had an estimated time of fifteen days, what impact would this have on your answer to part b?

12-16 Consider the following network for a small MIS project (all times are in days; network proceeds from node 1 to node 10):

Network

Job Activity Initial Node Final Node Estimated Time
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.