Review Questions

PM Milestone Project Management Templates

PM Milestone Project Management Templates

Get Instant Access

1. You are the project manager for Changing Tides video games. You have gathered the inputs for the Estimate Activity Durations process. Which of the following tools and techniques will you employ to produce the outputs for this process?

A. Activity list, expert judgment, alternatives analysis, analogous estimating, parametric estimating, three-point estimates, and reserve analysis

B. Activity list, expert judgment, analogous estimating, parametric estimating, and three-point estimates

C. Expert judgment, analogous estimating, parametric estimating, three-point estimates, and reserve analysis

D. Expert judgment, alternatives analysis, analogous estimating, parametric estimating, and three-point estimates

2. You are the project manager for Changing Tides video games. You have produced a project schedule network diagram and have updated the activity list. Which process have you just finished?

A. The Define Activities process, which identifies all the specific activities of the project

B. The Sequence Activities process, which identifies all the activity dependencies

C. The Develop Schedule process, which diagrams project network time estimates

D. The Estimate Activity Durations process, which estimates activity durations

3. Your project's primary constraint is quality. To make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools?

A. Three-point estimates

B. Analogous estimating

C. Reserve analysis

D. Parametric estimating

4. You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for its customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used?

A. Parametric estimating

B. Analogous estimating

C. Bottom-up estimating

D. Reserve analysis

5. All of the following statements describe the activity list except which one?

A. The activity list is an output of the Define Activities process.

B. The activity list includes all activities of the project.

C. The activity list is an extension of and a component of the WBS.

D. The activity list includes an identifier and description of the activity.

6. You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for its customers. Customers must register before being allowed to order wine over the Internet so that legal age can be established. You know that the module to verify registration must be written and tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following?

A. Preferential logic

B. Soft logic

C. Discretionary dependency

D. Hard logic

7. You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. Which of the following statements is true?

A. PDM is also the AON diagramming method and it uses one time estimate.

B. PDM is also the AOA diagramming method and uses logical relationships.

C. PDM is also the ADM diagramming method and its most common logical relationship is finish-to-start.

D. PDM is also the GERT method, which allows for conditions, branches, and loops.

8. You are working on a project that requires resources with expertise in the areas of hospitality management and entertainment. You are preparing your project schedule network diagram and know that you will use only finish-to-start dependencies. Which of the following diagramming methods does this describe?

D. Network template

9. Which logical relationship does the PDM use most often?

A. Start-to-finish

B. Start-to-start

C. Finish-to-finish

D. Finish-to-start

10. You are a project manager for Picture Shades, Inc. It manufactures window shades that have replicas of Renaissance-era paintings for hotel chains. Picture Shades is taking its product to the home market, and you're managing the new project. It will offer its products at retail stores as well as on its website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following statements is true?

A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates.

B. You calculated the activity dependency and the optimistic and pessimistic activity duration estimates.

C. You calculated the early and late start dates, the early and late finish dates, and float times for all activities.

D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

11. You are a project manager for Picture Shades, Inc. It manufactures window shades that have replicas of Renaissance-era paintings for hotel chains. Picture Shades is taking its product to the home market, and you're managing the new project. It will offer its products at retail stores as well as on its website. You're developing the project schedule for this undertaking. Looking at the following graph, which path is the critical path?

12. Use the following graphic to answer this question. If the duration of activity B was changed to 10 days and the duration of activity G was changed to 9 days, which path is the critical path?

13. Which of the following statements is true regarding the critical path?

A. It should not be compressed.

B. It allows for looping and branching.

C. The critical path technique is the same as PERT.

D. It's the duration of all tasks with zero float.

14. You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the weighted average or expected value?

15. You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation?

16. If you know the expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following?

A. The activity will take from 488 to 512 days.

B. The activity will take from 464 to 536 days.

C. The activity will take from 494 to 506 days.

D. The activity will take from 476 to 524 days.

17. If your expected value is 110 and the standard deviation is 12, which of the following is true?

A. There is approximately a 99 percent chance of completing this activity in 86 to 134 days.

B. There is approximately a 68 percent chance of completing this activity in 98 to 122 days.

C. There is approximately a 95 percent chance of completing this activity in 98 to 122 days.

D. There is approximately a 75 percent chance of completing this activity in 86 to 134 days.

18. You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of

A. crashing

B. fast tracking

C. resource leveling

D. adjusting the resource calendar

19. You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is overallocated. Which of the following statements is true?

A. You should use resource requirements updates to determine availability and smooth out resource overallocation.

B. You should use crashing to resource level the critical path tasks.

C. You should use resource leveling to smooth out resource assignments.

D. You should use fast tracking to resource level the critical path tasks.

20. What is one of the problems with project management software?

A. The project manager manages the software instead of the project.

B. Project duration calculations are sometimes approximate.

C. You cannot override the project management software decisions regarding schedules.

D. It's expensive and difficult to use.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Responses

  • rhianna bruce
    Which statement is true regarding activities not on the critical path?
    1 year ago
  • marmaduke
    Which of the following statement is true regarding the critical path of a project?
    1 year ago
  • Petra
    Which of the following is true for a critical activity?
    1 year ago

Post a comment