Monitor and Control Project Work Outputs

The outputs of the Monitor and Control Project Work process will also look familiar. They are as follows:

■ Change requests

■ Project management plan updates

■ Project document updates

Remember from Chapter 9 that change requests may take the form of corrective actions, preventive actions, or defect repairs. Corrective actions bring the work of the project into alignment with expected future performance. Preventive actions are implemented to help reduce the probability of negative project risks. Defect repairs either correct or replace components that are substandard or malfunctioning.

Project management plan updates may include updates to one or more of the management plans, including schedule, cost, or quality, and may require updates to the baselines, including scope, schedule, and cost performance.

Project document updates may include updates to forecasts, performance reports, and the issue log.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment