Inspection and Identification

Description of work: Inspect the building for asbestos, and identify all areas where it's found. Update the plan for removal (WBS 2.2) with each location identified.

Responsible organization: Adrian in Facilities will hire and oversee a contractor to perform this work.

Schedule milestones: Inspection and identification to start after contractor is identified and hired (no later than July 1). Work should be completed no later than September 15.

Contract information: Two contractors have been identified as qualified and experienced in this type of work. Contract process should close no later than June 12.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment