Timebased network diagram

Here you simply place the network diagram on a time-based graph. Draw the length of the arrows representing each task to equate with their actual durations as aligned with the bottom calendar of 97 days. Note that this figure shows float, or slack, the dotted lines that represent the flexibility in what time slot you determine to do the noncritical path tasks. Note also that the critical path, A, C, F, G, and H, a continuous arrow with no breaks, represents the critical path.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.