Should Have Started Tasks

When you print the Should Have Started Tasks report, as shown in Figure 13-24, you must supply a date by which tasks should have started. Project uses this date to determine which tasks appear on the report.

Figure 13-24: The Should Have Started Tasks report.

For each task on the report, Project displays planned start and finish dates, baseline start and finish dates, and variances for start and finish dates. Successor task information appears when a task on the report has a successor defined.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.