Receiving updates from team members

When team members record time on the Tasks page, they click either the Update All button or the Update Selected Rows button. In either case, they see a message like the one shown in Figure 20-35, indicating that an update was sent to the project manager for approval.

Figure 20-35: Project team members see notices that their project managers will be notified of actual work that they've recorded.

Figure 20-35: Project team members see notices that their project managers will be notified of actual work that they've recorded.

Note Functional managers can also track and approve actuals that are recorded by resources who are working for them. From the Resource Center of PWA, click the Approve timesheets link in the Actions pane.

When the project manager logs on to Project Web Access, the home page contains a link that isn't found on a team member's home page—the Updates link, as shown in Figure 20-36.

a Microsoft Office Project Web Access2D03 - projectserver - Microsoft Internet Explorer

File Edit View Favorites Tools Help

Q Back ▼ » [g] Vjj Search Favorites Media | ▼ . S

Address |gj http:/^projeclsecver^projectseiver/Home/HomePage.asp

"3 g Go Links

Altero5Olt"0fllcc

( 'iiProject Web Access

Home I Tasks | Projects | Resources | Status Reports | Updates | Risks | Issues 1 Documents | Admin

Home

Welcome to Project Web Access, Elaine Marmel

Actions:

| Homo Page | Updates

Change password You have 1 task change from a resource pending for approval.

Alert me about my tasks and status reports

Tasks la?^ You have no new tasks assigned to you.

Alert me about my resources on tasks and Risks status reports

You have no active risks assigned to you.

Go offline m

Work with Outlook to share calendar and task information,

Issues

You have no aciive issues assigned to you.

Copyright © 1990*2003 Microsoft Corporation. All rights reserved. License Agreement.

_O Trusted sites j

Figure 20-36: The project manager's home page contains an Updates section that contains information about pending updates.

When the project manager clicks the Update link, Project Web Access displays the View task changes submitted by resources page, as shown in Figure 20-37.

Update

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.