Multiple Baselines Gantt

The Multiple Baselines Gantt view is also based on the Gantt Chart view. The Multiple Baselines Gantt view enables you to see the first three baselines you save for your project. Each baseline is represented by a different color. In Figure 6-11, you see two baselines; two lines represent each task in the chart portion of the view.

The default table for the Multiple Baselines Gantt view is the Entry table, but you can change the table to any table you want using the techniques that are described in the section "Changing a Table," earlier in this chapter.

Figure 6-11: The Multiple Baselines Gantt view helps you compare the first three baselines you save.

You read more about baselines in Chapter 11.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment