Troubleshooting

You're trying to remove just the predecessor link from a task, but the successor link is removed at the same time

When you click a task and then click Unlink Tasks, all links are removed: predecessor, suc cessor, and any multiples. As a result, the scheduling of this task returns to the project start date or a start date entered as a constraint.

To remove just a single predecessor, click the task and then click Task Information on the Standard toolbar. In the Task Information dialog box, click the Predecessors tab. Click the task name of the predecessor you want to delete and then press the Delete key.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.