Review Availability Graphs for Multiple Resources

Select multiple resources in the Assign Resources dialog box and then click the Graphs button. The Resource Availability Graph shows graphs for each resource at the same time, using different colors for each resource (see Figure 7-6).

Figure 7-6. View the availability graphs and timesheets for several resources at one time.

Use the legend to map the graph to the resource, and also to include or exclude resources in the graph.

A different colored graph appears for each resource.

Resource availability by time period is shown in this timesheet for all selected resources.

Figure 7-6. View the availability graphs and timesheets for several resources at one time.

In the upper-right corner of the graph window, clear the check box for any resource whose graph you want to hide. The timesheet for all resources still shows below the graph.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.