Info

Resource Availability

1

Available From

Available To

Units

1/5/2004

3/26/2004

400%

3/29/2004

6/25/2004

300%

6/28/2004

8/27/2004

100%

-

::::::

Figure 6-10. Use the Resource Availability table in the Resource Information dialog box to specify multiple levels of maximum units throughout the project.

Tip Switch units from percentage to decimal

By default, maximum units are expressed as a percentage. You can represent them as a decimal if you prefer. Click Tools, Options and then click the Schedule tab. In the Show Assignment Units As A box, select Decimal. Now, instead of 100 percent, one full-time resource is shown as having 1 max unit.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment