To change the text style of your Gantt bar to include resource initials rather than the full resource name:

In the Resource Sheet, make sure that all resources have initials identified for them.

It doesn't necessarily have to be their actual initials—it can be a short name, a first or last name, a nickname, or whatever you want. Click View, Gantt Chart. Click Format, Bar Styles.

In the table area of the Bar Styles dialog box, make sure the Task row is selected.

In the lower half of the dialog box, click the Text tab. By default, Resource Names appears in the Right field.

Click the Right field and then click Resource Initials (see Figure 6-15). Click OK.

Task row

Text tab

Resource Initials

Figure 6-15. Use the Text tab in the Bar Styles dialog box to change the text that appears with the selected Gantt bar.

Task row

Text tab

Resource Initials

Figure 6-15. Use the Text tab in the Bar Styles dialog box to change the text that appears with the selected Gantt bar.

The resource initials you defined replace the full resource names next to the Gantt bars in the chart (see Figure 6-16).

Figure 6-16. Resource initials replace the full resource names next to the Gantt bars.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.