Controlling Outline Code Values

You can define settings to help users enter the correct values and format for outline codes. To do this, follow these steps:

1 Be sure that the Outline Code Definition dialog box is open and the code mask defined for the selected outline code.

2 To restrict codes to only those listed in a lookup table, select the Only Allow Codes Listed In The Lookup Table check box.

3 If users can enter codes not in a lookup table, you can make sure they enter values in each level of the code by selecting the Only Allow New Codes With Values In All Levels Of Mask check box.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.