Changing the Font for a View

By default, the font used throughout the Microsoft Project views is Arial 8 points. If you prefer a different font or size for one or all text elements in a particular view, follow these steps:

1 Click Format, Text Styles.

2 In the Item To Change box, be sure that All is selected.

This changes the font for all text elements in the current view in this project, including column and row headings, Gantt bar text, and all field data such as task and resource names.

3 Click OK.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.