Changing or Removing Links

To change or remove an existing task dependency, follow these steps: ^

1 Display the Gantt Chart or other view with a task sheet. j|

2 Select the successor task whose link you want to change. °

3 On the Standard toolbar, click Task Information and then click the Predecessors tab.

4 Click in the Type field for the predecessor you want to change and then select the type of task dependency you want it to be: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), Start-to-Finish (SF), or None. If you select None, the link is removed entirely.

Unlink Tasks

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.