Here the network consists of all the activities associated with a particular system such as the boiler plant, the crude oil loading and the quarry crushing and screening. A typical system network is shown in Figure 13.4. Advantages:

(a) Easy to establish and monitor the essential interrelationships of a particular system;

(b) Particularly useful when commissioning is carried out by system since a complete 'package' can be programmed very easily;

(c) Ideal where stage completion is required.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.