Materials Activity Developing VSM graphic

58 graphic artist hours @ $125/hr; after the hourly wage is calculated, add 125%, which represents 65% for quality control, 25% for supervisory overhead, 15% for administrative overhead, and 20% for estimate variance.

Task 1: Prepare graphics that represent the items that appear on each of the three slot machine s spinners. 8 graphic artist hours

Task 2: Prepare an overall graphic that represents the slot machine. 8 graphic artist hours

Task 3: Prepare a graphic that represents the slot machine ' s handle in several stages of motion. 4 graphic artist hours

Task 4: Prepare a page-header graphic that represents a montage of all four RLV hotels, including views outside and inside each plus shots of the hotel rooms, casinos, night-clubs, and restaurants. 32 graphic artist hours

Task 5: Prepare a Winner! graphic. 2 graphic artist hours

Task 6: Prepare a Sorry! graphic. 2 graphic artist hours

Task 7: Prepare a graphic that links to qLines airlines. 2 graphic artist hours