10 hours for marketing analyst @ $110/hr, plus 125% overhead

Task 1: Prepare print and media ads for new site. 8 hours

Task 2: Negotiate agreements for placement of web banners. 2 hours

You prepare the following spreadsheet:

From this spreadsheet, you have the information you need to prepare your project management software with the necessary tasks, activities, phases, durations, and team participants. From the requirements document, you can set your predecessors and successors, which, in this case, are in almost the exact order that you need them in. With the exception of the print and web banner ads, all of the other activities must occur in the order they ' re numbered.