Remember earned value analysis? Earned value analysis measures project performance. When project performance is waning, the project is likely missing targeted costs and schedule goals. The results of earned value analysis can signal that risks are happening within the project or that new risks may be developing.

For example, a schedule performance index (SPI) of .93 means the project is off schedule by 7 percent. A risk based on this value could mean that the project team is having difficulty completing the project work as planned. Additional work will continue to be late, the project will finish late, and quality may suffer as the team attempts to rush to complete assigned tasks.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment