Figure 6-3

Task relationships can vary, but finish-to-start is the most common.

Finish-to-Start

Task A must finish before Task B can start

Start-to-Start

Task A must start before Task B can start

Finish-to-Finish

Start-to-Finish

Task A must finish before TaskA must start before

Task B can finish Task B can finish

The portions of a network template are also known as subnets or fragnets. Subnets are often associated with repetitive actions within a network diagram. For example, each floor in a high-rise apartment building may undergo the same or similar actions during construction. Rather than complete the network diagram for each floor, a subnet can be implemented.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment