The project manager must also pay attention to the completion of activities on paths with float, not just the critical path. Consider a project that has eight different paths to completion. The project manager should first identify the critical path, but should also identify the float on each path. The paths should be arranged and monitored in a hierarchy from the path with smallest float to the path with the largest float. As activities are completed, the float of each path should be monitored to identify any paths that may be slipping from the scheduled end dates.

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.