Project Management Plan Updates

• Scope Baseline Updates. If the approved change requests have an effect upon the project scope, then the scope statement, the WBS, the WBS dictionary are revised and reissued to reflect the approved changes. The updated documents become the new project scope baseline.

• Other Baseline Updates. If the approved change requests have an effect on the project scope, then the corresponding cost baseline and schedule baselines are revised and reissued to reflect the approved changes.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.