Earned Value Measurement

The earned value technique in its various forms is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. The EVM methodology integrates scope, schedule, and resources, to objectively measure project performance and progress. It is a project management technique that requires the formation of an integrated baseline against which performance can be measured for the duration of the project. The principles of EVM can be applied to all projects, in any industry. EVM develops and monitors three key dimensions for each work package and control account:

• Planned value. Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a schedule activity or work breakdown structure component. It includes the detailed authorized work, plus the budget for such authorized work, allocated by phase over the life of the project. The total of the PV is sometimes referred to as the performance measurement baseline (PMB). The total planned value for the project is also know as Budget At Completion (BAC)

• Earned value. Earned value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. It is the authorized work that has been completed, plus the authorized budget for such completed work. The EV being measured must be related to the PV baseline and the EV measured cannot be greater than the authorized PV budget. The term EV is often used to describe the percentage completion of a project. Project managers monitor EV, both incrementally to determine current status and cumulatively to determine the long-term performance trends.

• Actual cost. Actual cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for a schedule activity or work breakdown structure component. It is the total cost incurred in accomplishing the work that the EV measured. The AC has to correspond in definition to whatever was budgeted for in the PV and measured in the EV (e.g., direct hours only, direct costs only, or all costs including indirect costs). The AC will have no upper limit; whatever is spent to achieve the EV will be measured.

Variances from the approved baseline will also be monitored:

• Schedule variance. Schedule variance (SV) is a measure of schedule performance on a project. It is equal to the earned value (EV) minus the planned value (PV). The EVM schedule variance is a useful metric in that it can indicate a project falling behind its baseline schedule. The EVM schedule variance will ultimately equal zero when the project is completed because all of the planned values will have been earned. EVM SVs are best used in conjunction with critical path methodology (CPM) scheduling and risk management. Formula: SV = EV - PV.

• Cost variance. Cost variance (CV) is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual costs (AC). The cost variance at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. The EVM CV is particularly critical because it indicates the relationship of physical performance to the costs spent. Any negative EVM CV is often non-recoverable to the project. Formula: CV= EV - AC.

The SV and CV values can be converted to efficiency indicators to reflect the cost and schedule performance of any project, to compare it against all other projects or within a portfolio of projects. The variances and indices are useful for determining project status and providing a basis for estimating project cost and schedule outcome.

• Schedule performance index. The schedule performance index (SPI) is a measure of schedule efficiency on a project. It is sometimes used in conjunction with the cost performance index (CPI) to forecast the final project completion estimates. An SPI value less than 1.0 indicates less work was completed than was planned. An SPI greater than 1.0 indicates the project is ahead of its planned schedule. The SPI is equal to the ratio of the EV to the PV. Formula: SPI = EV/PV.

• Cost performance index. The cost performance index (CPI) is a measure of cost efficiency on a project. It is the most critical EVM metric and measures the cost efficiency for the work completed. A CPI value less than 1.0 indicates a cost overrun for work completed. A CPI value greater than 1.0 indicates a cost underrun of performance to date. The CPI is equal to the ratio of the EV to the AC. Formula: CPI = EV/AC.

The three parameters of planned value, earned value, and actual cost can be monitored and reported on both a period-by-period basis (typically weekly or monthly) and on a cumulative basis. Figure 7-5 uses S-curves to display EV data for a project that is performing over budget and behind the work plan.

Actual And Plan Curve

Budget * at Completion (BAC)

Data Date

Time

Budget * at Completion (BAC)

Data Date

Time

Figure 7-5. Earned Value, Planned Value, and Actual Costs

Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Responses

  • Rhianna
    How is EV measured in projects?
    5 years ago
  • edgar escalante
    Which measurement method integrates scope, schedule, and costs (resources) to measure performance?
    2 years ago
  • nina bracegirdle
    Can cumulative EV be greater than BAC?
    8 months ago

Post a comment