The link between products and tasks

The importance of knowing what must be delivered cannot be underestimated, but there comes a point when estimates of time and cost must be produced. To do this, you need to know what tasks will be necessary to deliver each product.

Many products begin life in draft form using the product description as a guide. Once the draft has been completed, it is usual for a review to take place. This is where one of the quality methods referred to in the product description will be employed. As the product is compared with the product description, reviewers identify errors, which they note and to which the developer must attend. Once the amendments have been made, it should be possible to submit the product for final approval. The process can be summarised as:

e develop draft product; e review product; e amend product; e approve product.

When drawing up a plan, it is helpful to know the relationship between products and tasks. Products are created as a result of the tasks above or any others considered essential. Therefore, a sequence of tasks must be performed to deliver each product on the product flow diagram. When imagining the list of things that must be done to complete the project, it is sensible to think of a sequence of products (the product flow diagram) in which each has a life cycle. The list will look like this:

Product 1 Product 2

e Draft

e

Draft

e Review

e

Review

e Amend

e

Amend

e Approve

e

This important relationship will be revisited when the time schedule is developed. But before that something must be known of the techniques available to assist in estimating how long these products will take to develop and how much their development will cost.

Was this article helpful?

0 0
Project Management Made Easy

Project Management Made Easy

What you need to know about… Project Management Made Easy! Project management consists of more than just a large building project and can encompass small projects as well. No matter what the size of your project, you need to have some sort of project management. How you manage your project has everything to do with its outcome.

Get My Free Ebook


Post a comment